The deadline for this project is 31st of January 2005. The project has been started 15th of Octobre. To keep
momentum weekly meetings have been agreed upon starting November 16th.
Monday, 29th November 2004: Using of Hibernate, Eclipse, Twiki
Monday, 13th December 2004: Integration of Hibernate to Kaisersrot
Monday, 20th December 2004: First working prototype
Monday, 9th January 2005: Feature Freeze
Monday, 17th January 2005: Code Freeze and Code Review and Testing
Monday, 31st January 2005: Project finished
Next Sessions
16.11.2004: Introduction eclipse, setup wiki
22-26.11.2004: Overview of KaisersRot? project or sources by Braachi or Olli
29.11.2004: Overall system architecture and detailed technical questions, using cvs